Cycle Time Analysis Of Tipping Trailer Frame: A Case Study In A Heavy Equipment Industry
DOI:
https://doi.org/10.7166/25-1-636Keywords:
Arena simulation, cycle time, manufacturing, resource utilization.Abstract
A key element with which manufacturing industries should concern themselves in respect of cost and efficiency of operation is the cycle time for preparing their products. A reduction in operational time can result in dramatic improvements in both cost and efficiency. Unfortunately, cycle time problems are sometimes difficult to analyse: there are many factors related to this parameter. This paper presents a cycle time analysis of a tipping trailer frame in a heavy equipment industry. The cycle time analysis, based on the cycle time data collected by a time study, together with the use of an Arena software simulation, is outlined. From the results of this study, it was found that the manufacturing cycle time was 56 hours, and that resources were under-utilised.
Downloads
Downloads
Published
How to Cite
Issue
Section
License
Authors who publish in the Journal agree to the following terms:- Authors retain copyright and grant the Journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this Journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the Journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this Journal.