CLIENT PROJECT TIME SCHEDULE CONTROLS — AN EMPIRICALLY-BASED SYSTEM DYNAMICS CONCEPTUAL MODEL
DOI:
https://doi.org/10.7166/29-1-1680Keywords:
client schedule controls, design stage, project performance, System DynamicsAbstract
Different project participants often have different objectives and expectations, and implement different controls aimed at advancing their interests. This article investigates project controls taken by the client during the project design stage to improve project time schedule performance. Dynamic hypotheses and a System Dynamics conceptual model of client controls and their ripple effects are formulated in this article from a combination of the existing literature, mental models of project managers gathered through an embedded multiple-case study, and Systems Thinking. The results suggest that client controls that are aimed at improving project time schedule performance generate ripple effects that worsen the performance.
Downloads
Download data is not yet available.
Downloads
Published
2018-05-31
How to Cite
Chitongo, A. M., & Pretorius, L. (2018). CLIENT PROJECT TIME SCHEDULE CONTROLS — AN EMPIRICALLY-BASED SYSTEM DYNAMICS CONCEPTUAL MODEL. The South African Journal of Industrial Engineering, 29(1), 169–183. https://doi.org/10.7166/29-1-1680
Issue
Section
General Articles
License
Authors who publish in the Journal agree to the following terms:- Authors retain copyright and grant the Journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this Journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the Journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this Journal.