PROJECT ACTIVITY ANALYSIS WITHOUT THE NETWORK MODEL

Authors

  • S. Munapo Department of Decisions Sciences, University of South Africa

DOI:

https://doi.org/10.7166/21-1-68

Abstract

ENGLISH ABSTRACT: This paper presents a new procedure for analysing and managing activity sequences in projects. The new procedure determines critical activities, critical path, start times, free floats, crash limits, and other useful information without the use of the network model. Even though network models have been successfully used in project management so far, there are weaknesses associated with the use. A network is not easy to generate, and dummies that are usually associated with it make the network diagram complex

Downloads

Download data is not yet available.

Downloads

Published

2011-11-05

How to Cite

Munapo, S. (2011). PROJECT ACTIVITY ANALYSIS WITHOUT THE NETWORK MODEL. The South African Journal of Industrial Engineering, 21(1). https://doi.org/10.7166/21-1-68

Issue

Section

General Articles