DOES THE MRP LOGIC WORK FOR FINITE CAPACITY PLANNING AND OPERATIONS SCHEDULING?
DOI:
https://doi.org/10.7166/5-2-417Abstract
ENGLISH ABSTRACT: During the past five years, MRP based systems have increasingly been criticized for their inability to reduce inventory levels, meet due dates and to plan at an operational level. This paper suggests that the actual reasons for these problems are some fundamental flaws in the MRP logic and its assumptions. The logic of the optimized Production Technology (OPT) is suggested as an alternative approach that addresses the limitations of MRP based systems.
AFRIKAANSE OPSOMMING: Gedurende die afgelope vyf jaar het kritiek teen MRP-gebaseerde sisteme toegeneem. Die kritiek is hoofsaaklik dat MRP-sisteme vooraadvlakke nie voldoende verminder nie; beplande datums nie haal nie en ook nie op In operasionele vlak beplan nie. Hierdie artikel wil voorstel dat die rede hiervoor fundamentele foute in die MRP logika en aannames is. Die logika van "optimized Production Technology" (OPT) word as alternatief voorgestel, aangesien dit die probleemareas in die MRP-logika aanspreek.
Downloads
Downloads
Published
How to Cite
Issue
Section
License
Authors who publish in the Journal agree to the following terms:- Authors retain copyright and grant the Journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this Journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the Journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this Journal.